I have built a 3 phase power assist with 3 MultiPlusII 48/5000 / 70-50 and a GX color control.
I want a pre-alarm if the battery voltage falls below a certain threshold.
In the event of overloading the inverters or low batt, I want to switch off a big part of the load.
For that I need 2 independent virtual switches.
Is it possible to use only the Virual switch of the master to detect overload in the other phases? Or do I have to put the three virtual switches in parallel?
I tried to use the CCGX's alarm relay to detect overload and low batt but apparently that doesn't work, there is also little info about it.
Does anyone have an idea about this?
Thanks in advance.