Hi, i have a litte Problem ....
I have not seen before purchase, that the MP2 8k and 10k can not Operate in parallel mode :-(
I have the following Situation:
2 Holyday Homes... both have their own Fusebox and are connected to my MP2 10k (Offgrid)
I figured out that i could get overloads because the Peak consumption each Holyday Home is up to 7kw.
I Prefer to Split this 2 Holyday Homes to 2x MP2 10k (one for each Home)
This is Possible running the 2nd MP2 10k absolutely Standalone...
BUT i want do see the Consumtion on the Same Cerbo as well ... as L2 or whatever
(even it is logically a L1 + L1 szenario) i dont care how but the 2nd MP2 needs Battery informations for some Assists as well.
It this Possible and how to proceed ?
I have seen something with Dual phase 120 180 240 but i need 2x separated 230v ....
2x Single phase would be nice haha :-)