Hello,
According to Wiring Unlimited, all power sources should be distributed across the busbar. Right now, I have 4 lithium batteries, 2 MPPTs and 1 Quattro (soon to be 2) across a custom busbar. I now want to switch to a Lynx hence my dilemma.
According to various Victron documents, the batteries should be on one side and the chargers and inverters on the other of the Lynx Power-in and the Lynx Distributer. In my situation, I can't follow the recommendation of Wiring Unlimited in that case.
Question is: can I put 2 batteries on the Power-in and 2 batteries on the Distributor and distribute the other equipment across the 2 components accordingly?
Fideri