Good day.
I build an ups system for a client on emergency lights. This is in a mining area thus everything is in a panel. The system seems to be performing well. I have attached some pictures of the setup.
I need to get remote or scheduled testing running on the system.
Remote: Running VRM and test the inverter by ignoring the grid and run just off the battery pack for a set time.
Scheduled: Once a week ignore the grid for a set period to test the setup.
Is there a way to do it on the Multi Plus and not running it through a relay output?
Thank You!