Hi All
We have been coming across sites with high grid voltage, where we have some ESS systems installed these sites have PV on the Output side of the inverter. Due to our local requirements for PV inverters the grid voltage is so high that the PV won't ramp up to produce enough to charge the batteries.
We still have some legacy systems that run with the HUB2 v3 Assistant and its great for ignoring the AC input with PV on the output side.
Just checking to see if anyone else is in need/or there is a demand of a Ignore AC input on the ESS assistant when there are AC coupled PV inverters on the output, seen as though HUB2 has been depreceated.