Hi All,
We have 6 x 3kVa MPIIs working in parallel on a 3pH system. We have a 20amp 3pole breaker on the critical loads side protecting the system from overloads. Yet we continually get Overload warnings and when the Mains Grid drops out we often get full overloads.
The VRM load traces are set to 1 min and show no signs of these overloads.
The units are in an AC controlled room at 19deg.
The critical loads circuits had Earth Leakages that did not trip pre system install, yet tripped everytime the mains Grid dropped out. Client removed the ELs.
Lastly we have mppts charging the li ion battery and yet even with Phase Comp on ESS we have uneven power delivery, to the extent that 'spare' power is pushed back through the Mains Site meter though one or two of the phases, constantly.
System was installed by engineers with Victron training. System VRM has been reviewed by high level Engineers with Victron training. No solutions to date.
SLD For Victron.pdfSLD attached.