Two bmv-700 installation

Hello, i am installing a boat with a two bank 24v system switched 1/2/both/off. Also a victron split charge diode which requires both banks -ve to be permanently linked. I have bought 2 bmv-700 monitors as I would like to have visual information on both battery banks at the same time. Will this work and which side of the 2 shunts should the link cable be on?

BMV Battery Monitor
1 comment
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

Alexandra avatar image Alexandra ♦ commented ·

Hello @Sandisland. On the negative cables on the battery side for each separate bank is how the bmvs are meant to be installed if you are wanting readings of both banks.

0 Likes 0 ·
1 Answer
wkirby avatar image
wkirby answered ·

The DC link cable needs to go on the Load / Charger side of the shunt. The one and only connection to the Battery side of the shunt should be the battery negative of the battery to be monitored.

2 |3000