I am setting up two Quattro 5kw 12vdc 200 amp chargers in a split phase configuration.
I would like some advice on the lifepo4 battery configuration.
I have 24, 240ah 3.2 Vdc lifepo4 batteries.
Before I make my bus bars, is it better to have on large bank @ 6p4s @ 1440 ah or split the bank into a two 3p4s 720ah configuration?
I will be using an Orion bms 2 for management of the bank/s
Thx for any input...