Hi,
I currently have a Fronius primo 5kw inverter with 4kw of solar (2 arrays NW and NE) and am looking to add a victron Multiplus-II GX to provide some storage and redundancy for power outages.
I understand that with 4kw of solar and the inverter being only 3kw I will run into trouble with a grid outage if I have the solar inverter on the output of the multiplus due to the 1-1 rule.
Im wondering if there is any way to reduce the fronius down to 3kw as soon as the grid fails to make this work?
I guess any system would need to be very fast to avoid any inverter shutdown however if the solar inverter was to shut down for a short time then ramp back up slowly to a reduced output this might work?
Any thoughts are very much appreciated.
Thanks
Mike