Hi, can you please confirm we are configuring the system correctly.
Our application is to use the Multiplus ii to provide peak power when the grid cannot supply total power. In our case, the maximum grid power = 10 A @ 230 V = 2300 W, and we need to supply 4000 W for short periods. Our system is permanently connected to the grid without solar or any other power sources charging the batteries. And we wont to have the batteries 100 % charged at all times when not using the batteries.
We are connecting the Lynx Ion 1000 A BMS (we purchased prior to 400 A model being available) with 2x LiHE 100 Ah batteries) to the Venus GX. Please confirm that we use CAN bus for this. Do we need to enable any settings in the Venus GX? i.e. configure to 100 Ah @ 48 V?
When connecting the Multiplus ii, use VE Config 3 and add assistance ESS Energy Storage System. Please confirm that we DO NOT need to hardwire the allow-to-charge and allow-to-discharge signal contacts of the Lynx Ion BMS. Are there any other settings we need to add? The LiHE batteries are not available?
Does the 10 A grid input current get set in VE Config 3 or the Venus GX?
With VE Config 3, how do you use the "fake target with full options" and choose Multiplus ii?
Thanks for your assistance.
Mark