Here is picture how I have planned my system connections. Only power connections drawn monitoring and Cerbo missing in here. Do you see any mistakes or am I missing something?
This site is now in read-only archive mode. Please move all discussion, and create a new account at the new Victron Community site.
Here is picture how I have planned my system connections. Only power connections drawn monitoring and Cerbo missing in here. Do you see any mistakes or am I missing something?
Hi @beavis at a high level it looks good. If the budget can stretch I would consider a second shunt configured as a dc load meter so that you get accurate dc loads connected on the negative 24 volt Orion connection, a battery isolation switch, and possibly Orion load, Phoenix charger, and mppt solar isolation switches, I haven’t used them but depending on the type of batteries you might also benefit from installing a battery balancer to optimise the battery performance.