Does anyone have an example of G99 application? I need to submit one and I want to make it successful first time.
This site is now in read-only archive mode. Please move all discussion, and create a new account at the new Victron Community site.
Does anyone have an example of G99 application? I need to submit one and I want to make it successful first time.
Hi
Sorry I forgot that I had commented on this post... shortly after, I completed and submitted my G99 A1-1
it was approved in less than 15 hours
here is the thread I posted on it, with my application and line diagrams for example
https://community.victronenergy.com/questions/199051/has-anyone-had-their-g99-a1-1-approved-in-less-tha.html?childToView=199086#comment-199086
HTH
sorry not an Answer
I was just about to ask the same question..
I have bought a Multiplus 2 48/5000/70-50 230V and a 48v 5Kw battery system to start with. and might add a couple of solar pannels to top the batteries up
My DNO is WPD, now NG
and do I need to fill out the G99 or look at the G100 ??
when I look at the new Type Test Register the 48/5000 is now, a Fully type tested device for compliance with G99 Type A for the UK
It amazes me, that no one has made a walkthrough on how to fill out these forms, they look so hard to get right.