I'm pretty sure I know the answer to this. We have an upcoming system install with 3x Multiplus ii 5000/70 for an off grid install set up in 3 phase. The client needs 3 phase for about 4 hours per day. After that all loads are single phase with some bigger single phase equipment that will be used later in the day. These single phase loads are shop toold that maxes out a single Multiplus 2 ii 5000.
Can anyone imagine a way to have the system set up as 3 phase for part of the day and then paralleled for high load single phase loads the remainder of the time? I do realize that the actual wiring for the single phase will need to be creative if this is at all possible
I've racked my brain and don't believe it's possible other than increasing the number of parallel units but keeping the 3 phase.