question

bipedalprimate avatar image
bipedalprimate asked

Australia Grid Code N-bypass

What does N-bypass in the grid code selection for Australia mean?

1664419088713.png


Under what circumstances would you choose between the two options? ('no N-bypass' & 'with N-bypass')

Thanks,
Peter.

Multiplus-IIVEConfigure 3
1664419088713.png (76.2 KiB)
5 comments
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

Rob Duthie avatar image Rob Duthie commented ·
Hi

Neutral

0 Likes 0 ·
Show more comments
2 Answers
raymiller avatar image
raymiller answered ·

Then what is the difference between options A, B&C?

2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

raymiller avatar image
raymiller answered ·

Answering my own question above as to what A, B and C.

Setpoints are now defined by region of installation, as per the following categories:

  • Australia A: For large interconnected power systems, e.g. all Australian networks other than those specified below
  • Australia B: For small interconnected power systems, e.g. Western Power
  • Australia C: For isolated or remote power systems e.g. Horizon Power and TasNetworks
  • New Zealand: All systems in New Zealand
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.