Hello,
I am currently trying to add a solar setup to my house using the Victron Multiplus 12/3000/120 unit. The power company has told me that as part of their commissioning test my unit needs to have a 5 minute delay, after they turn the disconnect switch back on, before the inverter starts to send power to the house. From what i gathered they want to be able to turn the external disconnect switch to off and then back to on, but there needs to be a 5 minute delay between when they turn the switch back on and when the inverter sends power to the house. How would I set the inverter to do this?