Hi,
I'm just about to place an order for 2 x Multiplus II 48v/5000w, 1 x ET112 meter and 1 x Cerbo GX and just need to make sure this is all going to work as planned.
I've been looking through the documentation and forums for several months. From what I've read it looks like it should work but I just wanted to double check / get some assurance that I've not missed something.
I have a cheap overnight rate on Octopus Go, 7.5p/kWh as opposed to 35.05p/kWh during the daytime. We've programmed out Air Source Heat Pump to charge during the cheaper rate and during an excess solar production from the 4kw SMA Sunny Boy.
I want to be able to charge 2 sets of 48v 280Ah LifePo4 Batteries connected in parallel at the terminals only (not between each cell) and managed by a couple of Batrium Cellmate K9's to keep them balanced.
As my cheap rate window is only 4 hours and my safe battery capacity (80%) I'm limited in how many kWh I can put back in the batteries during those 4 hours - 13.44kWh per charger, hence 2 chargers. (2 x 70A)
Will the above setup in ESS mode, allow all the loads in the house to be powered by the Multiplus's and Sunnyboy whilst not exporting anything to the grid, and then charge the batteries back to 90% on the cheap rate electricity ?
or would I be better of with a Quattro 10kw which can charge at 140A native ?