We have our system setup and have been using ESS for years now. We have critical loads on AC output 1 and non-critical loads on AC output 2 so that critical loads continue to receive power during grid outages. Today for example we have a scheduled power outage for the whole day.
We have more than sufficient PV/battery power (over 2500w) now to also power the AC output 2 loads (around 1200w).
Is there a way to manually enable AC output 2 during such times? If not this might be a nice feature to add to the ESS settings on the CCGX.
This is what is currently being used without anything on AC output 2:
I have manually plugged in a few items into the AC output 1 circuit to show what is actually available on PV: