I'm looking at a primarily self consumption setup with 4kW grid connected PV, 4.8kW DC connected PV and 14 - 20kWh battery storage with provision for a generator, so the Quattro looks like the best option at present. The property is TN-C-S (PME).
The latest UK wiring regulations require the distributors earth to be connected to the islanded system neutral (N-E bond) during island mode,
for details. Figure 3 shows a relay for the N-E bond on the maintained loads side.
In grid connected mode the island mode isolator is closed and the N-E bond relay is open. In island mode the island mode isolator is open and the N-E bond relay is closed. There's a break before make timing sequence to follow.
How is this supported in ESS?
Many thanks
Kind regards
John