Over the past two months, I have commissioned several MPPTs. A recurrent problem following the firmware update is a low voltage system alarm. While checking the settings of the MPPT (Victron connect) I noticed that the MPPT failed to detect the right voltage level at startup and therefore leading to low voltage alarms.
I know how to fix the problem, but this situation is not ideal. Especially if I am giving support to a system installed in another country or that is connected via a can.bus (so far not supported for remote configurations with Victron Connect).
1. How could I verify and if necessary correct the system voltage remotely for a VE.Can connected MPPT device?
2. Did Victron notice this problem before? are you working to solve it?