Hi all. I have a multiplus 2 GX and pylontech 48v bank with bms.
The system works well with one string at the moment. The bms controls the MPPT via DVCC. The MPPT is connected via cable to the inverter.
I am adding 2 more strings with 2 new MPPT100/20. I can smart network the new MPPT via Bluetooth. My question is: how do I make sure the bms still controls the MPPT since I cannot impose which MPPT is the master? Do I have to physically connect all MPPT via cable (VE direct I think) or can I use the bluetooth network?
Many thanks for the answers.