Hello all.
I'm designing quite a large system for our off grid farm. About 15kw.
I will be using Panasonic HIT 325 Kuro as I all ready have some. These panels will fit the 250/100 well as I can have 5 parallel strings of 3 and be within temp adjusted max limits.
My question is:
My preferred option is to have 3 x smartsolar 250/100 mppt controllers paralleled going into 1 battery. This battery is quite large at 45Kw and will be lifepo4. The battery will then power 3 large inverters which will also be paralleled for 15kw single phase output.
I am however concerned that the 3 x smartsolars will not be able to synchronise to work well together. Is the patch that was proposed back in February going to happen? Or is there a hardware solution that I haven't seen yet that will enable the smartsolars to work together?
My other option is to split the system up into 3 sections and then just combine the 3 inverters. I'd rather not do this as I'd prefer to have one large 45kw battery as opposed to 3 x 15kw.
Thanks in advance.
Simon