I have an older Morningstar pro star 30 and want to replace with a new mppt 100/30. The old prostar has solar, battery and load wiring.
The 100/30 seems to only have solar and battery wiring.
What do I do with the load wires ?
This site is now in read-only archive mode. Please move all discussion, and create a new account at the new Victron Community site.
I have an older Morningstar pro star 30 and want to replace with a new mppt 100/30. The old prostar has solar, battery and load wiring.
The 100/30 seems to only have solar and battery wiring.
What do I do with the load wires ?
I have the same MPPT and it does not have a load terminal. I agree that you can run any loads of the battery bank, via fuses, off bus bars. I think the smaller Victron MPPTs have a load terminal.