Can we use two ET112 Meter to measure grid input on a 2 phase site? We have them in stock already. We have set them up but we cant seem to assign one to L1 and one to L2 because they seem to be locked in a 1 phase convention.
This site is now in read-only archive mode. Please move all discussion, and create a new account at the new Victron Community site.
Can we use two ET112 Meter to measure grid input on a 2 phase site? We have them in stock already. We have set them up but we cant seem to assign one to L1 and one to L2 because they seem to be locked in a 1 phase convention.
Hi,
no, this is not supported.
See here: Energy Meters start page [Victron Energy]
Q1, this is also true for two phases.