ET112 Energy Meters Two for Two phase

Can we use two ET112 Meter to measure grid input on a 2 phase site? We have them in stock already. We have set them up but we cant seem to assign one to L1 and one to L2 because they seem to be locked in a 1 phase convention.

split phase
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

1 Answer
markus avatar image
markus answered ·

Hi,

no, this is not supported.

See here: Energy Meters start page [Victron Energy]

Q1, this is also true for two phases.