Hello everyone.

my question is about grid parallel.

can i add to the Grid source the power of the Inverter when the load is high and prioritize the Pv power first

Can the load go over the max and be bigger then the nom power or the courant of the MultiPlus so the inverter can be underrated compared to the maximum courant required by the load


I have a 3 phases system with high load (2 pumps. AC, heat system plus the house consumption ) and i want to install 3 MP3000/48 in parallel so i use PV and when the load is high it powered from the grid.

i heard about grid assist but i have no idea how to make it run..... how to do that in practice

Thank you




MultiPlus Quattro Inverter Chargerbattery charging
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

1 Answer
michaelvausr avatar image
michaelvausr answered ·

You will find all the basic in the PDF paper "ESS Design & Installation Manual". Go to the ESS start page, see link: