Hi there.
Trying to size my system correctly with Victron products.
I am going to setup a 3 phase system using 3x multiplus II/3000/48V + 2x Smart Solar MPPT RS
I have a DIY 20 KWH battery with batrium BMS.
I will feed grid into the inverters.
- How will the multiplus act, if i pull more than 3000 watt from one phase? I see peak is 6000 watt, but there must be a limit for how long time it can deliver 6000w peak?
- What will happen if i install the system without a battery, for starters?
- Is it nessecary for the Victron to talk to my Batrium BMS - the unit should be able to measure the battery voltage by itself?
- Can i prioritize the system to deliver power from panels, before delivering from battery?