First post - A little guidance please on our design below:
We have 48 PV Panels each has an Enphase 215w micro inverter.
We have a genaration meter as part of our FIT
Our utility provider has installed a smart electricity meter to track half hourly usage
Would the below design work for us?
Our decision to connect the PV to the critical loads output (AC output 2) of the Quattro is to ensure the continuous supply from PV and battery in the event of a grid failure.
1) If we connected the panels to the Critical load, as mentioned in step 1 of the installation guide video at 7 minutes into it (https://www.victronenergy.com/live/ess:quick-installation-guide) - Would this work without the need for the additional ET112 meter?
2) With this setup, would we have use of the CCGX to show system energy flows and be able to control the system via the CCGX?
Thanks