Hello everyone,
I am currently running a system with the ESS assistant, and the start/stop generator.
I want the following :
1) When SOC >70% : Ignore grid input and use the PV/battey.
2) When grid failure : Use PV/battery until SOC drops down to 50%
The first point is working that to the Start/stop generator assistant.
However, in case of grid failure, I would like to run the batteries until a SOC of 50% before shutting down the system. How can I configure that in the Venus GX or in the VEConfigure.
I've only find a way to shut-down based on voltage...
Thanks you very much for your answer !
I have a system composed of the following elements :
- 1x multiplus 2000/48V
- 1x Venus GX
- 12 batteries ultracell 12V/200Ah
- 2x MPPT 150V/60A
- Communication cables Venus - MPPTs, and venus - Multplus