question

lunar avatar image
lunar asked

Pump running on MPPT daylight detection, can I get a signal 10 minutes before shutdown?

I have a Phoenix Inverter 48/3000 and an MPPT 150/85 some panels and battery. I am using it to run a pump during daylight hours using the day detection setting with a 30 minute minimum closed time. What I would like to do is be able to send a signal to the pump to run a a flush cycle say 10 minutes before shutdown. Anyone have any ideas on how to achieve this. Thanks

Relay
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

1 Answer
Daniël Boekel (Victron Energy Staff) avatar image
Daniël Boekel (Victron Energy Staff) answered ·

Hi @Lunar

You could use a timer in the Multi to postpone switching off by 10 minutes, and use this time for that.

https://www.victronenergy.com/live/assistants:overview_of_available_assistants

2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.