question

bosvark avatar image
bosvark asked

Offsite VE Configure

On a three phase system, can I configure the inverters separately on VE config (grid code, ESS etc.) and firmware updates before going to site? Then once on site do the phase (master, slave) configuration as I don't have three phase at my workshop?

VEConfigure 3
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

1 Answer
Daniël Boekel (Victron Energy Staff) avatar image
Daniël Boekel (Victron Energy Staff) answered ·

Hi @Bosvark

You can set it up without having 3 phases in your workshop: just use battery power.

But of course you can also setup 3 phase later, just not via remote configure, you have to configure 3 phase setup on site before you can change settings via internet.