Dear All
I am thinking to install three MP2 (5K) on a three phase line coming from the grid.
They supply the house that is used for accommodation units so each unit has it's own 230V supply between (L1/N) / (L2/N) & (L3/N). [NO three phase equipment on site]
My Question:
Will the MP2 be OK with an unbalanced load i.e. lets say two units are occupied but the third unit stays empty of 2 nights - later on all three is occupied, then only one etc. (and all possible options).
(NO Generator, just RS 450/100 "on roof" with -+ 25 kWh battery)
(GRID will still be there for "support" if SOC is low or draw is higher then .... )
(Main objective is to lower Grid cost - but the grid is not always reliable so hence for the time being - No PV-AC (fronius). Maybe later)
Any advise will be appreciated.