Looking to get some advice on the operation of the Multiplus 2.
As MP2 does not have a G100 Cert. I have been looking at way to remove the need.
We have a small farm in the UK with a single phase 230v supply so do not need a massive system but more than your average family home.
Our DNO has advised an initial export limit of 3.68Kw on enquiry.
I should be able to install a MP2 (firmware 510) as G98 with the 16A limit.
Would it be possible to operate 2 or 3 MP2 5k in parallel. But have only one unit connect to the incoming supply, providing charging to a battery system and passthrough. the other units would operated as off grid, using a battery (system would also have DC coupled PV).
As operating in parallel all AC out would be combined to provide a single phase output.