Hi Everyone
We have a client that wants to go off grid. He would however need a 200KWP array to generate the required amount of total yield daily... That leaves us with a bit of a problem as the new Maxi GX will give us 25 Mppts but that still only means maximum array of 148KWP using 250/100A Smartsolars...
Any ideas or suggestions? had been thinking going AC coupled Hybrid but seems like a waste as his KVA requirement on the inverter side is only 60KVA, so going 180KVA to accommodate PV inverters for the array seems like a waste...
Any advise would be appreciated...
Kind regards
Elster Vermeulen