I noticed several time that my system goes in passthrou when I use a planer or techno squaring machine or a bandsaw machine (inductive loads). Never used all toghether and of course they do not exceed the power provided by system composed by:
2 x Multiplus II 48 V 5 Kva in parallel :
3 x Smart Solar charge regulator;
Lynx power in - Lynxs Shunt - Lynxs Distributor;
2 x Lifepo4 14 Kwh batteries (total 28 Kwh);
11 Kw of solar panels.
Despite batteries fully charged and solar panesl at their top of production if I start one of those loads the system goes in passthrou.
If I start all the appliances in the house like oven dishwasher washing machine hairddryer etc.etc
I can gather the 8 Kw available even for hours with no problem.
Am I missing something ?
Any help or suggestion higly appreciated.