I think I am getting close with this system. It has six 200w 8.3A 24v panels, with three in series two in parallel producing 1.2KW. Currently this is what I am putting together for a grid connected system that stores power in batteries and feeds excess power back into the public grid.
Components are...
-two Multiplus-II 48/3000/35-50 120v
-Victron 250/70 SmartSolar charge controller
-Cerbo GX
-Lynx Power In
-Lynx Shunt VE.Can
-Lynx Distributor
-Victron VM-3P75CT energy meter
-Chins 48v LiFePO4 battery
-six Rich 200w 24v 8.3A solar panels
I am in the United States. Is this a reasonable system now that this Multiplus has UL approval? What am I missing? Anything I should change? What problems should I anticipate?
Thanks in advance, Happy New Year!