Following case:
- 3 phase Quattro-II 5kVA, generator on input 1 and grid on input 2.
- Client has a PV installation which could not be installed on the output of the Quattro's.
- The PV power is being measured with an EM24 with RS485 (connected the proper way, as told in the manual)
- On Venus OS, the energy meter is told to be installed on input 2.
- The installed assistant is ESS with grid setpoint 0W.
All the information is available, but the installation is not working.
Actual faults:
- PV inverter is shown on output, even if told it's on the input.
- ESS NOT WORKING. And this is more critical, because now the installation is just consuming energy.
It shows the energy is flowing back but instead of taking the energy and charging the battery, it is just showing.