Hello all,
I have some doubts regarding proper wiring. My system is:
- SmartSolar 100/20 connected to 3x100W solar panels connected in parallel
- SmartSolar 75/15 connected to 1x100W solar panel
- 2x170Ah 12V batteries connected in parallel
- 1000W pure sine inverter
Charge controllers are synced (VE.Smart Network) and everything is working flawlessly.
I've ordered SmartShunt 500A and I have following questions:
- Can I connect both charge controllers battery negative wires to SmartShunt "load minus" terminal?
- I'm using load terminals on SmartSolar 75/15 to run 12V led strip in streetlight mode. Should negative wire of led strip be directly connected to SmartShunt "load minus" terminal and led strip positive connected to SmartSolar load positive terminal (Option 1 in diagram)? Or SmartSolar load negative should also be connected to SmartShunt "load minus" terminal (Option 2 in diagram)?
- If I don't connect SmartSolar load to SmartShunt and only put them on the same VE.Smart Network, will it be able to sum up total power consumption (SmartSolar load terminals consumtion + everything else that is going through SmartShunt)?
Edit: Fuses are not added to the diagram but I have them!
Appreciate your time and help!
Regards,
Vaso