question

hybridizd avatar image
hybridizd asked

Hybrid / Off-grid System and ESS

Hi All,

I am currently running an hybrid/off grid system that has a mains connection for battery charging when required, and would like to explore what benefits ESS can provide for my system specifically. Any ideas and suggestions are greatly appreciated!

System info;

2 x Multiplus II 48/5000/70 in parallel
10KWH 48V Battery bank (2 x 48V 5KWH Batteries)
Cerbo GX
Victron MPPT 250/85 with 12 x 415W panels connected

I am not currently planning on feeding back into the grid, but happy to explore this later as there is more involved. I believe ESS can be setup grid feed-in can be disabled?


20230727-153452.jpg

Multiplus-IIESSoffgridsystem design
2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.

1 Answer
Rob Duthie avatar image
Rob Duthie answered ·

Hi

Yes go into settings ESS and set feed in parameters as required.

Regards

Rob D

NZ

2 |3000

Up to 8 attachments (including images) can be used with a maximum of 190.8 MiB each and 286.6 MiB total.