I’m installing a system into a detached shop with a sub-panel fed from the main home. I want to prioritize PV and battery over grid input, and cannot have grid feed-in. Grid will be used only when batteries fall below a certain voltage or loads exceed a certain point. I also want to be able to charge the batteries from grid if necessary.
What is the best way to accomplish this?
Equipment:
*2x Quattro 10k setup for 240v split phase
*2x MPPT RS 450/200
*Cerbo GX with Touch 50
*48v 900Ah LiFePO4 battery bank with no SOC/BMS communication