Hi Community,
I have recently been installing a set up which eventually will enable me to fully offgrid.
I have 2 x 5kva multiplus 2 inverters and at present 4 x Pylontec US5000c batteries controler by cerbo GX.
Once installed I added a MPPT RS 450/200 pv unit and temporarily connected 4 x 550W panels to string 1 to allow me to power up the building where the install is sighted which is remote from the main property ( to be connected later)
I have to day connected in series to string 4 6 x 550w panels and to string 3 4 x 550w panels. Switching on string 4 gave an additional 2200w which I expected but then when switching on string 3 string four drops to 1450 ish watts. It would seem to me that my system is limiting the pv overall to somewhere around 4300 watts but i can't figure out why.
Can anyone advise why this would be happening.