Hi guys
I have this one installation 48/5000 easy solar with a 5 kWh Dyness battery (recommended the 10kwh to client) with Ess which seems to work fine for a few loadshedding cycles and then after just go back to not switching over fast enough when the grid fails. (Did happen twice now that I get it sorted for a few days )Time delay is about 20 seconds before the loads come on. When I simulate grid lost by switching off main switch the system works 100%
This problem only happens when Eskom strike loadshedding
I have read previous chats on forum but just can’t seem to get this one sorted out. I have 2 other exact shame installations which is working 100%
Just need some advice or what you guys might think it could be.
Thanks for your time