Hi,
What can be done to remedy this situation:
- grid set-point at 50W, grid feed-in is switched off for AC And DC, but still power is being fed to the grid. In this instance I am charged money for illegally feeding power back - energy is being wasted.
On the other hand, if I put the grid set-point to something like 300w, then power is being pulled from the grid despite plenty of power being available from PV. It should not be necessary to pull power from the grid. In this instance I am also being charged, but this time for pulling power, which is at least a bit better than the previous situation, where energy is being frittered away.
How can this be remedied ? Do I possibly have a faulty grid meter (ET112) that needs replacing ?