Hello community
My current set up lay on 12V battery bank with MPPT 100/50. 5 solar modules connected as parallel due to not even in specs in wattage... maybe that is wrong. 4 modules are same specs (12V/75Wp) and 1 module is 12V/200Wp. According controller capacity was thinking to add one more panel of 12V/200Wp, reaching max wattage controller capacity. Is very much appreciated if you instruct me for best string/s connection layout, in order to minimize cables size and maximize efficiency ?
Thank you in advance
BR
Aris