System Overview:
Victron Multiplus-II (5KVa) is connected to Grid with Grid Feedback allowed.
Pylontech Batteries
SMA Sunnyboy (5KVa) PV Inverter on AC1.
7KW Petrol Generator - Manual Start.
AC-In is on a change over switch. Position 1 (Default) is the Grid, Position 2 is the generator.
In the event of grid failure, which configuration should be changed on the CCGX to prevent Generator overload and any power feedback to the generator?
Is setting AC1 from Grid to Generator enough?
Thank you in advance!