Hello I have an EM24, Multiplus2, cerbogx and a mppt 150/70.
The MP2 is connected to L1.
If I now switch the ESS grid metering from inverter/charger to the EM24 and 1000 watts are consumed on L3, for example, it starts to feed into L1. But I do not want this. It should only feed into L1 if enough is being consumed here. Gridsetpoint is 100W and it makes no difference if I set Multiphase regulation to Total of all phases or Indivbidual Phase.
Grid feed-in is completely switched off.
EDIT:
I have checked in: https://www.victronenergy.com/media/pg/Energy_Storage_System/en/multiphase-regulation---further-information.html that With the "Single Phase" option selected, the (single phase) ESS uses the battery to balance only L1 to 0W. L2 and L3 are visible on the CCGX but are not used by the ESS in any way.
This is exactly what I want. But it doesn't work like that...
Please help. Thanks
MrYoshii