We have installed a 3-phase system consisting of 3 x Victron 8 Kva's and Fronius Symo 20.0-3-M. The phase’s are not balanced by default as loads don't draw at same time. The problem is now that with one phase drawing higher loads than other two, the Fronius is throttling to the highest phase from loads, the two other phases (equivalent to the one or more loads being fed by Fronius via the Victron’s) then is being feed into the grid past the Victron energy meter.
How can we limit this feed into grid?
Tcp is enabled, PV inverter has been assigned, but at the TCP finds no IP address. Even if we enter the address in manually it does not change the feed into grid. All settings on Fronius match. Out of ideas to try and make this work.