Hi everyone! Need help!
My current setup Multiplus II 48/5000/70 with CT sensor - Cerbo GX and 320ah 14S managed by Batrium BMS (talks via VE can) runs ESS on 1st phase.
Everything being running good, so I decided to add one more inverter on second phase. (Not in parallel, 3 phase or split phase (I'm in Australia 240V per phase here already).
It appears I can't setup second inverter in ESS unless I add second GX servo as well. As soon I daisy chain VE Bus I get error. Running "quick VE config" only gives me parallels, split, 3 phase options.
For my application I only need ESS to run on 2 phases - can't run 3 phase setup. (3rd phase managed by other system already).
Running 2 independent Cerbo GX with MP II would work but than I'll have issue with BMS or have to use another battery with separate BMS ? I assume I can't split one VE Can to talk to 2 separate GXs
Any info would be great! Maybe I'm missing something or there is another way around it?
Thank you
Eugene